
November 19, 2026
APTEL Restores the ROE from 11% to 13% ROE for Extended PPA Period by Holding That GERC Is Bound by Its Own Tariff Regulations and Tariff Order
Gujarat State Electricity Corporation Limited v. Gujarat Electricity Regulatory Commission & Anr., Appeal Nos. 301 of 2026...Read More
November 11, 2026
HERC Rejects Review Petition, Holds Section 142 Proceedings Cannot Reopen Concluded Issues and Enforcement Proceedings Must Remain Within the Four Corners of the CGRF Order
Case No. HERC/RA 07 of 2026 | Judgment dated 15 October 2026 The Haryana Electricity Regulatory Commission (‘HERC’), vide order...Read More
November 6, 2026
The Hon’ble Appellate Tribunal Upholds Admissibility of Price and Quantity Variations in Transmission Capital Cost: Feasibility Report Estimates Are Indicative, Not Sacrosanct
The Hon’ble Appellate Tribunal for Electricity (“Appellate Tribunal”), by its judgment dated 9 September 2026 in TANGEDCO v....Read More
October 27, 2026
No Reopening of Settled Claims: PSERC Rejects a Fresh LPS Claim After the Appellate Tribunal’s Judgment Order dated 13 October 2026 | Petition No. 47 of 2026
The Punjab State Electricity Regulatory Commission (“PSERC”), vide its order dated 13 October 2026 in M/s Indian Sucrose Limited...Read More
October 26, 2026
APTEL Verdict: Under-utilisation of Transmission Assets No Bar to Commercial Operation or Recovery of Charges through the PoC Mechanism
The Hon’ble Appellate Tribunal for Electricity has upheld POWERGRID’s contention that a transmission asset placed in regular...Read More
October 19, 2026
APTEL Clarifies but Does Not Reopen, The Arbitrability Question Under Section 79(1)(f): Review Petition No. 6 of 2026
Tata Power Company Limited v. Gujarat Urja Vikas Nigam Limited & Ors., Review Petition No. 6 of 2026 decided on 17 September...Read More
October 9, 2026
An Unchallenged Regulatory Order Bars a Fresh Petition on the Same Tariff — Appeal No. 325 of 2026
Haryana Power Purchase Centre v. M/s Siwana Solar Power Projects Ltd. & Haryana Electricity Regulatory Commission decided on...Read More
September 29, 2026
Karnataka High Court upholds validity of Regulation 5.8(vii)(a) of the GNA Regulations, 2022, sets aside Single Judge’s directions permitting CTUIL to process Renewable Power Park Developer’s (RPPD) applications without prior government authorisation
In a common judgment dated 28.08.2026 in Writ Appeal (“W.A.”) No. 1961 of 2025 and seven connected appeals, the Division Bench of...Read More
September 26, 2026
PSERC Holds Pre-Existing PPAs Without a Change in Law Clause Bind the Parties, Dismisses Solar Generators’ Claim for Pass-Through of RCM-GST on Land Lease Rentals
By a common order dated 19.08.2026, the Punjab State Electricity Regulatory Commission (“State Commission”) has dismissed the...Read More
July 25, 2026
APTEL Sets Aside APERC’s Deduction of Variable Charges for Monthly Availability Shortfall: Energy Charges Cannot Be Penalised
The Appellate Tribunal for Electricity (“Appellate Tribunal”) in its judgment dated 03.07.2026, has ruled in favour of Hinduja...Read More
July 22, 2026
APTEL Upholds that Delay in Securing Long-Term Access (LTA) is not a valid Force Majeure and Therefore, Scheduled Delivery Date under PPA Cannot be Unilaterally Extended
In a judgment dated 03.07.2026 in Appeal No.183 of 2020, the Appellate Tribunal for Electricity (Appellate Tribunal) has...Read More
July 21, 2026
