logologo
  • Home
  • About Us
  • Team
  • Expertise
    • Energy and Infrastructure
    • Property Law
    • Regulatory & Compliance
    • Litigation & Dispute Resolution
      • Civil Litigation
      • Commercial Litigation
    • Corporate & Commercial
    • Alternate Dispute Resolution
    • Gaming & Sports
    • Real Estate
    • Private Client Practice
      • Estate & Succession Planning
      • Family Settlements, HUF & Partition
    • Labour & Employment
    • Insolvency and Bankruptcy
  • Legal Alerts
    • Articles
    • Recent News
  • Contact Us
011-36865659
  • Home
  • About Us
  • Team
  • Expertise
    • Energy and Infrastructure
    • Property Law
    • Regulatory & Compliance
    • Litigation & Dispute Resolution
      • Civil Litigation
      • Commercial Litigation
    • Corporate & Commercial
    • Alternate Dispute Resolution
    • Gaming & Sports
    • Real Estate
    • Private Client Practice
      • Estate & Succession Planning
      • Family Settlements, HUF & Partition
    • Labour & Employment
    • Insolvency and Bankruptcy
  • Legal Alerts
    • Articles
    • Recent News
  • Contact Us
logologo
  • Home
  • About Us
  • Team
  • Expertise
    • Energy and Infrastructure
    • Property Law
    • Regulatory & Compliance
    • Litigation & Dispute Resolution
      • Civil Litigation
      • Commercial Litigation
    • Corporate & Commercial
    • Alternate Dispute Resolution
    • Gaming & Sports
    • Real Estate
    • Private Client Practice
      • Estate & Succession Planning
      • Family Settlements, HUF & Partition
    • Labour & Employment
    • Insolvency and Bankruptcy
  • Legal Alerts
    • Articles
    • Recent News
  • Contact Us
011-36865659
  • Home
  • About Us
  • Team
  • Expertise
    • Energy and Infrastructure
    • Property Law
    • Regulatory & Compliance
    • Litigation & Dispute Resolution
      • Civil Litigation
      • Commercial Litigation
    • Corporate & Commercial
    • Alternate Dispute Resolution
    • Gaming & Sports
    • Real Estate
    • Private Client Practice
      • Estate & Succession Planning
      • Family Settlements, HUF & Partition
    • Labour & Employment
    • Insolvency and Bankruptcy
  • Legal Alerts
    • Articles
    • Recent News
  • Contact Us
November 17, 2025 by R Associates Recent News 0 comments

CERC Upholds Revocation of Connectivity for 300 MW Wind Project; Denies Relief to Inox Green in Bhuj-II Transmission Dispute

In an order dated 17.11.2025, the Central Electricity Regulatory Commission (CERC) has declined relief to Inox Green Energy Services Limited (IGESL) concerning its 300 MW connectivity at Bhuj-II Pooling Station, while upholding the regulatory framework governing connectivity and General Network Access (GNA).

The decision provides important clarity on compliance obligations under the GNA Regulations and the treatment of connectivity in cases of project delays.

1. Connectivity Linked to SECI-awarded Wind Projects

The matter pertains to IGESL’s 300 MW wind power project in Kutch, Gujarat, developed pursuant to six Power Purchase Agreements (PPAs) executed with Solar Energy Corporation of India (SECI).

While SECI granted multiple extensions of the Scheduled Commissioning Date (SCOD) up to 31.08.2022, the project remained uncommissioned beyond the extended timelines.

2. Regulatory Compliance Under GNA Framework

The Commission examined compliance requirements under the Connectivity and GNA Regulations, including:

  • Achievement of Commercial Operation Date (COD)
  • Demonstration of financial closure
  • Adherence to prescribed timelines for connectivity utilisation

The record indicated that these milestones had not been fulfilled within the applicable regulatory timelines.

3. Connectivity and GNA: Regulatory Consequences of Non-Compliance

Pursuant to the applicable regulatory framework, steps were taken in relation to the connectivity granted to the Petitioner, including:

  • Issuance of notices seeking compliance with regulatory requirements
  • Invocation of applicable provisions under the GNA Regulations
  • Action in respect of connectivity and associated bank guarantees

The Commission observed that such measures were taken in accordance with the governing regulations and applicable procedures.

4. Consideration of Project Delays

The Petitioner attributed delays to factors such as:

  • Land allocation challenges in Gujarat
  • Delay in readiness of evacuation infrastructure
  • Pandemic-related disruptions
  • Financing constraints

While these factors were noted, the Commission emphasised that connectivity under the regulatory framework remains contingent upon timely compliance with prescribed milestones.

5. No Automatic Right to Retain or Reallocate Connectivity

The Petitioner sought retention of connectivity under alternative routes and requested that the 300 MW capacity be reserved in its favour.

The Commission declined these prayers, holding that:

  • Connectivity is conditional and not absolute in nature
  • Continued non-utilisation of allocated capacity cannot be sustained indefinitely
  • Allocation of transmission capacity must align with regulatory discipline and system efficiency

6. Delineation of Issues Beyond Scope

The Commission clarified that certain issues including

  • Extension of SCOD
  • Liquidated damages under PPAs

are being examined in separate proceedings and were not adjudicated in the present matter.

Read Judgement

Share

Related Posts

CERC permits Power Exchanges to charge up to 2pkWh as fee
by Anumeha SmitiMay 15, 20230 comments

CERC allows Power Exchanges to charge a transaction fee up to the ceiling limit of 2 paisa/kWh from either party to the transaction

Read More
by R AssociatesJuly 9, 20240 comments

Regulatory Clarity on Utilization of Spare Land for Data Centers

Read More
tribunal authority
by R AssociatesMay 8, 20230 comments

Tribunal Lacks authority to negotiate or establish New Agreements on behalf of Parties

Read More
APTEL Relinquishment
by R AssociatesJanuary 15, 20260 comments

APTEL Reaffirms Statutory Primacy: Relinquishment Charges Upheld Despite Force Majeure

Read More

Leave a Comment! Cancel reply

Your email address will not be published. Required fields are marked *

The Anatomy of a PPA Dispute in India: From Notice to RemedyPrevious Post
India’s Labour Law ResetNext Post

About Us

Serving clients with unwavering dedication and ethical principles for more than a decade. Step in confidently knowing that you are in capable hands.

Service Offerings

  • Company Registration in India
  • Business Setup in India
  • Startup Lawyers in India
  • Media and Entertainment Legal Services
  • Real Estate Lawyers in Delhi
  • Gaming & Sports Law Services
  • Insolvency and Bankruptcy Legal Services
  • Infrastructure and Energy Law Firm in Delhi

Other Services

  • Labour and Employment Law Services
  • Regulatory Compliance Law Services
  • Litigation & Dispute Resolution Lawyers
  • Corporate & Commercial Law Services
  • Alternate Dispute Resolution Legal Services
  • UK | R Associates
  • US | R Associates

Stay Connected

O-24/A, Jangpura Extension, New Delhi -110014

Email: [email protected]

Phone: 011-36865659
Get Directions

  • LinkedIn
  • Twitter

Copyright © 2023 R Associates. All Rights Reserved.

As per the rules of the Bar Council of India, we are not permitted to solicit work and advertise. The user acknowledges that there has been no advertisement and personal communication from R Associates, any information obtained or material downloaded from this website is completely of the user’s volition and any transmission, receipt, or use of this site would not create any lawyer-client relationship. In cases where the user has any legal issues, he/she in all cases must seek independent legal advice.

  • ↓
  • Reach Out To Us